THUNDER BAY, ONTARIO--(Marketwired - Feb. 9, 2017) - Benton Resources Inc. (TSX VENTURE:BEX) ("Benton" or "the Company") and its joint venture partner Nordmin Engineering Ltd. ("Nordmin"), is pleased to release the results of an updated positive preliminary economic assessment ("PEA"). Included with this PEA update is the announcement on the advanced Environmental Assessment (EA) progress for its Cape Ray Gold Project, located approximately 20 kilometers northeast of Port aux Basques, Newfoundland.

The 2016 drilling program provided the team with numerous insights into the nature of this project. It allowed the team to revise the geologic and resource models to better represent the intrinsic nature of the mineral resource, and make a re-assessment to the overall approach and layout of the proposed mine design.

The updated results of the PEA include a pre-tax net present value at a 7 percent discount rate of $82.2 million with a pre-tax internal rate of return of 40 percent and a post-tax NPV at a 7 percent discount rate of $56.9 million with a post-tax IRR of 34 percent.

The PEA is based on the mineral resource estimate completed by Marc Jutras, P.Eng., M.A.Sc., outlined in the National Instrument 43-101 technical report update.

Highlights from the PEA, with the base-case gold price of $1,306 (U.S.) per ounce and an exchange rate of $1.26 CAD/USD, are as follows (all figures in Canadian dollars unless otherwise stated):

  • Pre-production Capital is $54.5 million with a contingency of 10% included within the initial capital. Pre-production is for a 2 year period.
  • Sustaining Capital $27 million for the Life of Mine.
  • Pre-tax NPV (7%) of $82.2 million and internal rate of return of 40%.
  • Post-tax NPV (7%) of $56.9 million and internal rate of return of 34%.
  • Pre-tax Net Revenue of $146.8 million over 9 year LOM.
  • Post-tax Net Revenue of $104.3 million over 9 year LOM.
  • Positive Cash-flow is realized in year 2.
  • 2.8 million tonnes of mill feed averaging a combined 3.3 g/t gold and 9.7 g/t silver.
  • Mill operates at average tonnage of 1,000 tonnes per day.
  • Total production of 291,000 ounces of gold and 553,000 ounces of silver.
  • Gold recovery of 98% and Silver recovery 63%.

Chris Dougherty, P.Eng., President of Nordmin stated "the PEA Update is something we felt necessary given the extensive work we have completed in the last 6 months. The understanding developed through the completion of the 5000 metre drilling campaign in November has positively changed our overall knowledge and understanding of these zones". 

All of the economics are completed on Indicated and Inferred categories of the resource model.

The table below compares the change in IRR and NPV from the 2016 PEA and the 2017 revision.

  Pre-Tax
Year 2017 2016
IRR 40% 29%
Discount rate NPV ($ million)
0% 146.85 88.43
7% 82.19 48.43
10% 64.36 36.74
15% 42.66 22.07
  After Tax
IRR 34% 24%
Discount rate NPV ($ million)
0% 104.26 63.43
7% 56.86 32.64
10% 43.72 23.64
15% 27.66 12.35

Mineral Resources - Effective date of February 1, 2017

51 ZONE + 04 ZONE + 41 ZONE+WGH - INDICATED MINERAL RESOURCES 1,2,3
Au Cut-Off
(g/t)
Tonnage
(,000)
Average Au
(g/t)
Total Au oz.
(,000)
Average Ag
(g/t)
Total Ag oz.
(,000)
1.0 4,148 2.75 367 9.76 1,302
1.5 2,783 3.5 313 11.67 1,045
2.0 1,990 4.21 269 13.13 840
2.5 1,486 4.87 233 14.71 703
3.0 1,155 5.49 204 16.14 599
3.5 928 6.03 180 17.26 515
4.0 754 6.57 159 18.15 440
4.5 621 7.06 141 19.12 382
5.0 512 7.56 124 20.1 331
51 ZONE + 04 ZONE + 41 ZONE + WGH ZONE - INFERRED MINERAL RESOURCES 1,2,3
Au Cut-Off
(g/t)
Tonnage
(,000)
Average Au
(g/t)
Total Au oz.
(,000)
Average Ag
(g/t)
Total Ag oz.
(,000)
1.0 2,770 1.77 158 6.57 585
1.5 1,199 2.54 98 9.22 355
2.0 725 3.07 72 10.46 244
2.5 357 3.99 46 13.22 152
3.0 204 4.95 32 15.7 103
3.5 144 5.65 26 15.32 71
4.0 105 6.38 21 15.83 53
4.5 96 6.59 20 16.06 49
5.0 77 7.03 18 16.34 41
  1. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the Mineral Resources estimated will be converted into Mineral Reserves. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
  2. The CIM definitions were followed for the classification of Measured, Indicated, and Inferred mineral resources.
  3. The quantity and grade of reported Inferred Resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as an Indicated or Measured Mineral Resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured Mineral Resource category.

"The receipt of a positive PEA demonstrating strong economics over the life of mine is a major milestone for Benton," stated Stephen Stares, President and CEO of Benton. "We see numerous opportunities to further enhance the economics through additional studies and exploration with a high probability for resource expansion and good potential for new discoveries across the property. We will now focus on advancing the Cape Ray project toward feasibility through additional exploration, environmental permitting and further studies". Benton recognizes that this is an undeveloped area of Newfoundland. As such, protecting the environment is of great importance. To facilitate the development of a sustainable project, Nordmin, the joint partner, has experts on staff to complete the necessary studies required concerning environmental monitoring, assessment and permitting matters.

The Company has initiated work towards firming up costs and preparing a prefeasibility study. Apart from further metallurgical studies, the work will include drilling and tailings characterization as well as environmental baseline studies, hydrology monitoring, flora and fauna studies. A NI 43-101 technical report for Cape Ray PEA will be filed on SEDAR (www.sedar.com) within 45 days.

The reader should be cautioned that the PEA is preliminary in nature. It contains inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the results of the PEA will be realized.

Cape Ray combined open-pit and underground mine

Key economic assumptions and results

Description Units Value
Total mineralized rock mined Kt. 2,805
Gold grade g/t 3.29
Silver grade g/t 9.73
AuEq grade g/t 3.43
Gold recovery % 98
Silver recovery % 63
Gold price US$/oz. 1,306.15
Silver price US$/oz. 18.97
Exchange Rate $USD/$CAD   1.262
Payable gold metal oz. 291,341
Payable silver metal oz. 553,162
Total net revenue $ million 492.0
Total capital costs (Project and Sustaining) $ million 85.4
Overall Operating costs (total) $ million 259.7
Overall Operating cost (AuEq) US$/ozAuEq 664.6
(AISC) Overall cost (AuEq) US$/ozAuEq 883.0
Payback period years 2
Mine Life years 9
Pre-tax Cumulative net cash flow $ million 146.9
Post-tax Cumulative net cash flow $ million 104.3
Pre - tax NPV (7%) $ million 82.2
Pre - tax IRR % 40
Post - tax NPV (7%) $ million 56.9
Post - tax IRR % 34

Capital and operating costs

The Cape Ray Project has been envisioned as an open-pit mine with starter pits for all the zones and one underground mining operation for the 51 zone. Open-pit and underground mining are anticipated to be completed by contract mining companies. The equipment will be supplied by the contractor that is awarded the work.

Grid electrical power will provide the majority of the electrical power to the project over the life of the mine. The work force is expected to come from the Isle aux Morts area for the operation of the Mill. The rest of the workforce will be the responsibility of the contractor.

Total capital cost estimate

Capital Expenditures Contingency $ million
Sustaining Capital Expenditures by Zone    
PIT 41 5% -
PIT 51 5% -
PIT 04 5% -
Window Glass 5% 2.89
U.G. 51 5% 24.20
Permitting 10% 2.17
Road work (Quote from Adams Construction) 10% 3.53
Overburden Removal 10% 1.07
Surface Infrastructure - General 10% 2.84
Ore and Waste Pads (3) - Mine & Mill 10% 0.44
Surface Shop 10% 1.68
Land Costs 10% 0.91
Mill Capital 10% 33.34
Tailings 10% 3.82
Water Treatment Plants / Testing 10% 0.56
Power Distribution to Mill 10% 1.16
Working Capital 10% 0.84
Engineering for Capital 10% 1.17
OH & In-directs 10% 1.00
Mine Closure 0% 3.82
Total Capital Expenditures   85.44

Production and Processing

Operations for the Cape Ray project is planned to have both Open Pit and Underground Mining. Each zone will be campaigned separately with the use of contractors. The initial estimated mill feed will come from the 04 zone. Once the 04 pit is completed the 51 pit will commence to be mined followed by the 41 pit. The underground development for the 51 zone will start during the mining of the 41 pit. The start of the Window Glass pit will begin once the 41 pit is mined. The Window Glass pit and 51 underground zone will be mined simultaneously. All the zones will give a current mine life of 9 years combined at a milling through-put of 1,000 tonnes per day. The process plant includes conventional crushing, grinding, gravity, and whole ore cyanide leach. A gold and silver doré will be produced on site. Process reagents will be removed from the plant tailings prior to placement in a tailings management facility. 

Mineral Resources Avg. Au
g/t
Avg. Ag
 g/t
Tonnes
(,000)
Pit 41 2.31 8.38 520
PIT 51 4.53 12.40 350
PIT 04 4.67 11.52 208
Window Glass 1.65 5.68 1,155
U.G. 51 and Stock Pile 6.27 16.87 573
Total     2,805

* The mill feed tonnes in the mine plan include Inferred Resources. The reader is cautioned that Inferred Resources are considered too speculative geologically to have economic considerations applied to them that would enable categorization as Mineral Reserves. There is no certainty that Inferred Resources will ever be upgraded to Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Going forward, the team will be working on laying out the next 5000 metre drilling program that will commence this summer, which will also include some geotechnical drilling to support the pit designs and other work on site and continue to work towards environmental milestones to progress the project to the next phase.

Qualified Persons and 43-101 Disclosure

Marc Jutras, P.Eng., M.A.Sc., Principal, Mineral Resources, at Ginto Consulting Inc. is an independent Qualified Person as per National Instrument 43-101, and is responsible for the estimation of Cape Ray's mineral resources. Mr. Jutras has reviewed and verified that the technical information contained herein is accurate and approves of the written disclosure of same.

About Benton Resources Inc. (TSX VENTURE:BEX)

Benton Resources Inc. is a well-funded Canadian-based junior with a diversified property portfolio in Gold-Silver, Nickel, Copper, and Platinum group elements.

Clinton Barr (P.Geo.), V.P. Exploration for Benton Resources Inc., is the qualified person responsible for this release has prepared, supervised the preparation or approved the scientific and technical disclosure in the news release.

On behalf of the Board of Directors of Benton Resources Inc., Stephen Stares, President

THE TSX VENTURE EXCHANGE HAS NOT REVIEWED AND DOES NOT ACCEPT RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

The information contained herein contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements."

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to gold price and other commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.

Stephen Stares
(807) 475-7474
(807) 475-7200
www.bentonresources.ca