ZUG, Switzerland, Jan. 31, 2019 /CNW/ - Katanga Mining Limited (TSX: KAT) ("Katanga" or the "Company") is pleased to announce its ore reserve and mineral resource estimates as at December 31, 2018.

Key Updates: Mineral Resources

  • Overall, the measured and indicated mineral resource for Kamoto Copper Company SA ("KCC") (in which the Company has a 75% interest) decreased by 7.9 million tonnes since December 31, 2017, and inferred mineral resource decreased by 2.9 million tonnes since December 31, 2017, attributable to depletion due to mining activities in 2018.

  • There are no changes in the measured, indicated or inferred mineral resources reported for T-17 Open Pit / T-17 Underground Mine, Kananga Mine and Tilwezembe Open Pit Mine, as no mining and no geological work was undertaken in these areas in 2018.

  • A reconciliation table comparing the 2017 and 2018 mineral resource estimates is set out in Annexure A.

Key Updates: Ore Reserves

  • The result of the December 31, 2018 ore reserve estimate is a net decrease of 5.5 million tonnes of ore reserves since December 31, 2017, which is attributable to depletion due to mining activities in 2018.

  • A reconciliation table comparing the 2017 and 2018 ore reserves is set out in Annexure B and the key mining parameters which inform the ore reserve estimates are set out in Annexure C

KATANGA MINING LIMITED
CONSOLIDATED ORE RESERVES
AND MINERAL RESOURCES 1, 2, 3, 4, 5, 6, 7, 8, 9
as at December 31, 2018

Ore Reserves

Mt

%TCu

%TCo

Proved

8.7

3.56

0.55

Probable

124.0

3.15

0.51

Proved & Probable

132.7

3.18

0.52





Mineral Resources




Measured

16.3

3.58

0.57

Indicated

259.3

3.64

0.54

Measured & Indicated

275.6

3.64

0.54

Inferred

164.9

3.78

0.44

 

More detailed ore reserve and mineral resource estimates are as follows:

KATANGA MINING LIMITED
PROVED AND PROBABLE ORE RESERVES 1, 2, 5, 6, 7, 9
as at December 31, 2018


Ore Reserves

Mt

%TCu

%TCo

KTO

26.6

3.40

0.54

Mashamba East Open Pit

31.6

2.15

0.60

T-17 Underground

11.3

3.65

0.62

KOV Open Pit

57.5

3.72

0.48

KITD Tailings (KCC PE525)

2.8

1.42

0.16

KITD Tailings (GCM PE8841)

2.9

1.45

0.17

TOTAL

132.7

3.18

0.52

 

KATANGA MINING LIMITED
MEASURED AND INDICATED MINERAL RESOURCES 1, 2, 3, 4, 5, 6, 8, 9
as at December 31, 2018

Measured and Indicated Mineral Resources

Mt

%TCu

%TCo

KTO

77.7

3.92

0.48

Mashamba East Open Pit

57.8

1.72

0.63

T-17 Open Pit/T-17 Underground

13.6

3.89

0.61

KOV Open Pit/KOV Underground/KTE Underground

106.8

4.80

0.53

Kananga Mine

4.1

1.61

0.79

Tilwezembe Open Pit

9.5

1.89

0.60

KITD Tailings

6.1

1.44

0.17

TOTAL

275.6

3.64

0.54

 

KATANGA MINING LIMITED
INFERRED MINERAL RESOURCES 1, 2, 3, 4, 5, 6, 8, 9
as at December 31, 2018

Inferred Mineral Resources

Mt

%TCu

%TCo

KTO

48.4

3.83

0.38

Mashamba East Open Pit

15.9

2.72

0.51

T-17 Open Pit/T-17 Underground

5.2

4.21

0.98

KOV Open Pit/KOV Underground/KTE Underground

77.6

4.40

0.38

Kananga Mine

4.0

2.00

0.98

Tilwezembe Open Pit

13.8

1.75

0.60

KITD Tailings

0.0

0.00

0.00

TOTAL

164.9

3.78

0.44

 

Notes:

  1. The ore reserve and mineral resource estimates have been prepared in accordance with the classification criteria of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves prepared by the Joint Ore Reserves Committee of the Australasian Institute of Mining and Metallurgy, Australian Institute of Geoscientists and Minerals Council of Australia, as amended ("JORC Code"). If the definitions and classification standards adopted by the Canadian Securities Administrators' National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101") had been used instead of those of the JORC Code, the estimates of mineral reserves and mineral resources would be substantially similar to the estimates of ore reserves and mineral resources presented here.
  2. The mineral resource estimates have been prepared by, or under the supervision of, Christiano Santos Goncalves, (MAusIMM CP (Geo) 306 079) and the ore reserve estimates have been prepared by, or under the supervision of, Jacobus Lotheringen, PrEng each of Golder Associates Africa Pty Ltd, who are each a qualified person under NI 43-101. 
  3. Mineral resources are inclusive of ore reserves.
  4. Mineral resources which are not ore reserves have not necessarily demonstrated economic viability.
  5. The ore reserve and mineral resource estimates are for KCC's entire interest in such ore reserves and mineral resources, whereas the Company owns 75% of KCC. La Générale des Carrières et des Mines ("GCM") and La Société Immobilière du Congo, state-owned mining companies in the Democratic Republic of Congo, own the remaining 25% of KCC. 
  6. Numbers may not add due to rounding.
  7. Unless otherwise noted, the Company's ore reserves are estimated using appropriate cut-off grades based on an assumed long term price of $6,500 per tonne of copper and long term price of $60,000 per tonne of cobalt. Ore reserves are estimated using appropriate process recoveries, operating costs and mine plans that are unique to each property and include estimated allowances for dilution and mining recovery.
  8. Unless otherwise noted, the Company's mineral resources are estimated using appropriate lithological interpretations, grade compositing and grade estimation techniques for copper and cobalt.
  9. The Company's normal data verification procedures have been used in collecting, compiling, interpreting and processing the data used to estimate ore reserves and mineral resources. Independent data validation has also been performed as a part of Company's standard peer review procedure.
  10. The total KITD Reserve of 5.7 Mt resides on lease boundaries of KCC's operating permit PE525 and Gécamines operating permit PE8841.  KCC has the legal right to mine the tailings discharged from its KTC operations as per the provisions of the joint venture agreement concluded with Gécamines.

Qualified Person and Technical Report
This press release was prepared under the supervision of Mr. Tahir Usmani, P.Eng, APEGA, Chief Mine Planning Engineer of Katanga and a 'qualified person' as such term is defined in NI 43-101. Mr. Tahir Usmani has reviewed and approved the contents of this press release.

The Company's technical report entitled "NI 43-101 Technical Report on the Material Assets of Katanga Mining Limited, Lualaba Province, Democratic Republic of Congo" dated March 31, 2018 is filed under the Company's profile on SEDAR at www.sedar.com.

Cautionary Note to US Investors concerning estimates of Measured, Indicated and Inferred Mineral Resources

The above tables use the terms "Measured, Indicated and Inferred Mineral Resources" in accordance with the ore reserves and mineral resource categories of the JORC Code. We advise US investors that while these terms are recognized and required by Canadian regulations, the US Securities and Exchange Commission does not recognize them. "Inferred mineral resources" have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of inferred mineral resources will ever be upgraded to a higher category. In accordance with Canadian rules, estimates of inferred mineral resources cannot form the basis of feasibility or other economic studies. US investors are cautioned not to assume that any part or all of the inferred mineral resource exists, or is economically or legally mineable.

Unless otherwise specified, all $ amounts referred to in this press release are U.S. dollars.

About Katanga Mining Limited

Katanga Mining Limited operates a major mine complex in the Democratic Republic of Congo producing refined copper and cobalt. The Company has the potential to become Africa's largest copper producer and the world's largest cobalt producer. Katanga is listed on the Toronto Stock Exchange under the symbol KAT.

Forward Looking Statements
This press release may contain forward-looking statements, including, but not limited to, statements concerning the mineral resources and ore reserves of the company, economic feasibility thereof, and the overall expected improvement of recoveries and grades. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or describes a "goal", or variation of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

All forward-looking statements reflect the Company's beliefs and assumptions based on information available at the time the statements were made. Actual results or events may differ from those predicted in these forward-looking statements. All of the Company's forward-looking statements are qualified by the assumptions that are stated or inherent in such forward-looking statements, including the assumptions listed below. Although the Company believes that these assumptions are reasonable, this list is not exhaustive of factors that may affect any of the forward-looking statements. The key assumptions that have been made in connection with the forward-looking statements include the following: the operations of the Company during the ramp up of production following the commissioning of the Whole Ore Leach ("WOL") Project remaining consistent with management's expectations, there being no significant disruptions affecting the operations of the Company whether due to labour disruptions, supply disruptions, power disruptions, rollout of new equipment, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at KCC being consistent with the Company's current expectations; continued recognition of the Company's mining concessions and other assets, rights, titles and interests in the DRC; political and legal developments in the DRC being consistent with its current expectations; the continued provision or procurement of additional funding from Glencore for operations; the completion of the T17 Underground Mine and the Power Project (as defined in the Annual Information Form of the Company for the year ended December 31, 2017 dated April 2, 2018); that new equipment performs to expectations; the exchange rate between the US dollar, South African rand, British pound, Canadian dollar, Swiss franc, Congolese franc and Euro being approximately consistent with current levels; certain price assumptions for copper and cobalt; prices for diesel, natural gas, fuel oil, electricity and other key supplies being approximately consistent with current levels; production and cost of sales forecasts for the Company meeting expectations; the accuracy of the current ore reserve and mineral resource estimates of the Company (including but not limited to ore tonnage and ore grade estimates); and labour and material costs increasing on a basis consistent with the Company's current expectations.

Forward-looking statements involve known and unknown risks, future events, conditions, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, prediction, projection, forecast, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the actual results of current exploration activities; actual results and interpretation of current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of copper and cobalt; possible variations in ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of exploration, development or construction activities, delays due to strikes or other work stoppage, both internal and external to the Company as well as those factors disclosed in the Company's current annual information form and other publicly filed documents. Although Katanga has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events, or otherwise, except in accordance with applicable securities laws.

Annexure A

Katanga Mining Limited Mineral Resource Reconciliation at December 31, 2018 and 2017

Classification

Project Area

2018

2017

Variance

Mt

%TCu

%TCo

Mt

%TCu

%TCo

Mt

Measured

KTO

12.1

3.90

0.59

12.2

3.90

0.59

(0.1)

Mashamba East Open Pit

0.0

0.00

0.00

0.0

0.00

0.00

0.0

T-17 Open Pit/T-17 Underground

4.2

2.66

0.51

4.2

2.66

0.51

0.0

KOV Open Pit/KOV Underground/KTE Underground

0.0

0.00

0.00

0.0

0.00

0.00

0.0

Kananga Mine

0.0

0.00

0.00

0.0

0.00

0.00

0.0

Tilwezembe Open Pit

0.0

0.00

0.00

0.0

0.00

0.00

0.0

KITD Tailings

0.0

0.00

0.00

0.0

0.00

0.00

0.0

Subtotal

16.3

3.58

0.57

16.4

3.58

0.57

(0.1)

Indicated

KTO

65.6

3.92

0.46

65.9

3.92

0.46

(0.3)

Mashamba East Open Pit

57.8

1.72

0.63

60.0

1.68

0.62

(2.2)

T-17 Open Pit/T-17 Underground

9.4

4.44

0.65

9.4

4.44

0.65

0.0

KOV Open Pit/KOV Underground/KTE Underground

106.8

4.8

0.53

110.4

4.75

0.53

(3.6)

Kananga Mine

4.1

1.61

0.79

4.1

1.61

0.79

0.0

Tilwezembe Open Pit

9.5

1.89

0.60

9.5

1.89

0.60

0.0

KITD Tailings

6.1

1.44

0.17

7.8

1.49

0.16

(1.7)

Subtotal

259.3

3.64

0.54

267.1

3.60

0.53

(7.8)

Measured and Indicated

KTO

77.7

3.92

0.48

78.1

3.92

0.48

(0.4)

Mashamba East Open Pit

57.8

1.72

0.63

60.0

1.68

0.62

(2.2)

T-17 Open Pit/T-17 Underground

13.6

3.89

0.61

13.6

3.89

0.61

0.0

KOV Open Pit/KOV Underground/KTE Underground

106.8

4.80

0.53

110.4

4.75

0.53

(3.6)

Kananga Mine

4.1

1.61

0.79

4.1

1.61

0.79

0.0

Tilwezembe Open Pit

9.5

1.89

0.60

9.5

1.89

0.60

0.0

KITD Tailings

6.1

1.44

0.17

7.8

1.49

0.16

(1.7)

TOTAL

275.6

3.64

0.54

283.5

3.60

0.54

(7.9)

Inferred

KTO

48.4

3.83

0.38

48.5

3.83

0.38

(0.1)

Mashamba East Open Pit

15.9

2.72

0.51

18.3

2.85

0.47

(2.4)

T-17 Open Pit/T-17 Underground

5.2

4.21

0.98

5.2

4.21

0.98

0.0

KOV Open Pit/KOV Underground/KTE Underground

77.6

4.40

0.38

78.0

4.40

0.38

(0.4)

Kananga Mine

4.0

2.00

0.98

4.0

2.00

0.98

0.0

Tilwezembe Open Pit

13.8

1.75

0.60

13.8

1.75

0.60

0.0

KITD Tailings

0.0

0.00

0.00

0.0

0.00

0.00

0.0

TOTAL

164.9

3.78

0.44

167.8

3.79

0.44

(2.9)

 

Notes: See the footnotes on page 3-4 of this press release.

Annexure B

Katanga Mining Limited Ore Reserve Reconciliation as at December 31, 2018 and 2017

Mining operation

2018 Reserve Estimate

2017 Reserve Estimate

Variance

Mt

%TCu

%TCo

Mt

%TCu

%TCo

Mt

KTO

26.6

3.40

0.54

26.9

3.40

0.54

-0.3

T-17 Underground

11.3

3.65

0.62

11.3

3.65

0.62

0.0

Mashamba East Open pit

31.6

2.15

0.60

32.1

2.13

0.60

-0.5

KOV Open Pit

57.5

3.72

0.48

60.5

3.70

0.48

-3.0

KITD Tailings (KCC PE525)

2.8

1.42

0.16

4.4

1.51

0.16

-1.6

KITD Tailings (GCM PE8841)

2.9

1.45

0.17

2.9

1.46

0.17

0.0

Total

132.7

3.18

0.52

138.1

3.15

0.51

-5.5


 

Notes: See the footnotes on page 3-4 of this press release.

Annexure C

Operation

Mining
Dilutions

Mining and
Pillar Losses

Geological
Losses

Cut-off Grade
(Cu)

Processing
Recoveries
(Cu)

Processing
Recoveries
(Co)

KTO Underground

5% to 10%

5%

5%

1.50%

76.2%

65%

KOV Open Pit

20%

5%

0%

0.65%

85%

65%

T17 Underground

8%

8%

8%

1.20%

85%

65%

Mashamba East Open Pit

7.9%

5%

0%

0.65%

85%

65%

 

SOURCE Katanga Mining Limited

View original content: http://www.newswire.ca/en/releases/archive/January2019/31/c3588.html